Aug 31,2017

77.44% PROGRESS CONSTRUCTION

The progress of work

Project Task

Piling Work
0%
Soil Protection Work
100%
Excavation Work
0%
Basement Work
0%
Super Structure Work
97%
Architectural Work
65%
Mechanical , Electrical and Pumbling Work (MEP)
0%
External Work
0%
Lift Works
0%
Staff house or Office
0%
Demolition Building
0%
Preliminaries
79%

 

Modify Date:Aug 31,2017