May 31,2018
95.89% PROGRESS CONSTRUCTION
The progress of work
Piling Work
0%
Soil Protection Work
100%
Excavation Work
0%
Basement Work
0%
Super Structure Work
100%
Architectural Work
97%
Mechanical , Electrical and Pumbling Work (MEP)
0%
External Work
95%
Lift Works
0%
Staff house or Office
0%
Demolition Building
0%
Preliminaries
100%
Modify Date:May 31,2018