Apr 30,2018

86.34% PROGRESS CONSTRUCTION

The progress of work

Project Task

Piling Work
0%
Soil Protection Work
95.00%
Excavation Work
100.00%
Basement Work
0%
Super Structure Work
100.00%
Architectural Work
83.80%
Mechanical , Electrical and Pumbling Work (MEP)
0%
Interior Work
0%
External Work
61.72%
Staff house or Office
100.00%
Demolition Building
0%

 

Modify Date:Apr 30,2018