May 31,2018

57.09% PROGRESS CONSTRUCTION

The progress of work

Project Task

Soil Protection Work
100.00%
Excavation Work
100.00%
Basement Work
99.00%
Super Structure Work
90.40%
Architectural Work
45.70%
Mechanical , Electrical and Pumbling Work (MEP)
0%
Staff house or Office
75.00%
Demolition Building
0%
Footing Work
100.00%
Preliminaries
72.00%

 

Modify Date:May 31,2018