Jan 31,2018

9.78% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
0%
Piling Work
0%
Soil Protection Work
83.58%
Excavation Work
95.53%
Basement Work
35.00%
Super Structure Work
0%
Architectural Work
0%
External Work
0%
Lift Works
0%
Staff house or Office
100.00%
Demolition Building
0%
Preliminaries
23.97%

 

Modify Date:Jan 31,2018