Jul 31,2018

93.36% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
0%
Piling Work
100.00%
Soil Protection Work
100.00%
Excavation Work
100.00%
Super Structure Work
100.00%
Architectural Work
94.25%
External Work
90.00%
Staff house or Office
100.00%
Demolition Building
100.00%
Basement Work
0%

 

Modify Date:Jul 31,2018