Sep 30,2017

7% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
0%
Piling Work
22.00%
Soil Protection Work
50.00%
Excavation Work
60.00%
Basement Work
20.00%
Super Structure Work
7.10%
Architectural Work
0%
External Work
0%
Staff house or Office
100.00%
Demolition Building
0%

 

Modify Date:Sep 30,2017