Oct 31,2017

8.55% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
0%
Piling Work
80.00%
Soil Protection Work
70.00%
Excavation Work
10.71%
Basement Work
0%
Super Structure Work
0%
Architectural Work
0%
Interior Work
0%
External Work
5.86%
Staff house or Office
100.00%
Demolition Building
0%

 

Modify Date:Oct 31,2017