Jul 31,2018

11.53% PROGRESS CONSTRUCTION

The progress of work

Project Task

Soil Protection Work
0%
Excavation Work
0%
Basement Work
0%
Super Structure Work
17.45%
Architectural Work
0%
External Work
18.56%
Preliminaries
46.49%

 

Modify Date:Jul 31,2018