Oct 31,2017

10.28% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
0%
Piling Work
22.00%
Soil Protection Work
58.00%
Excavation Work
72.00%
Basement Work
25.00%
Super Structure Work
7.70%
Architectural Work
0%
External Work
0%
Staff house or Office
100.00%
Demolition Building
0%

 

Modify Date:Oct 31,2017