Mar 31,2018

20.1% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
5.00%
Piling Work
100.00%
Soil Protection Work
75.00%
Excavation Work
100.00%
Basement Work
59.00%
Super Structure Work
16.00%
Architectural Work
7.00%
External Work
0%
Staff house or Office
100.00%
Demolition Building
0%

 

Modify Date:Mar 31,2018