Aug 31,2019

69.52% PROGRESS CONSTRUCTION

The progress of work

Project Task

M & E Work
44.85%
Piling Work
100.00%
Soil Protection Work
100.00%
Excavation Work
100.00%
Basement Work
100.00%
Super Structure Work
100.00%
Architectural Work
37.90%
External Work
41.24%
Staff house or Office
100.00%
Demolition Building
0%

 

Modify Date:Aug 31,2019