Mar 31,2018

3.59% PROGRESS CONSTRUCTION

The progress of work

Project Task

Piling Work
0%
Soil Protection Work
12.66%
Excavation Work
15.98%
Basement Work
0%
Super Structure Work
0%
Architectural Work
0%
Mechanical , Electrical and Pumbling Work (MEP)
0%
Interior Work
0%
External Work
10.40%
Staff house or Office
80.00%
Demolition Building
0%

 

Modify Date:Mar 31,2018