Jul 31,2018
8.9% PROGRESS CONSTRUCTION
The progress of work
Piling Work
0%
Soil Protection Work
47.94%
Excavation Work
55.14%
Basement Work
0%
Super Structure Work
0%
Architectural Work
0%
Mechanical , Electrical and Pumbling Work (MEP)
0%
Interior Work
0%
External Work
10.79%
Staff house or Office
100.00%
Demolition Building
0%
Modify Date:Jul 31,2018